|
UPDATE!!!!!!!!!!!!!!!!!!!
27 June 2007: A phone call
was received today from an independent contractor employed by Ara Macao
asking (demanding?) that the historical information on this Website about
Ara Macao be taken down because it is "misleading and inflammatory."
I have reviewed the information presented here, and all of it reports
events as they occurred during the Ara Macao EIA approval process.
This entire process was a very significant one for the Placencia Peninsula
and surrounding areas. It occupied public debate for over an entire
year, it brought Peninsula communities and people together, and ultimately
has made everyone on the Peninsula much more aware of environmental and
development issues. It also raised issues that continue to need to
be answered, such as the capacity and recharge rate of the aquifer that
provides water to the people of the Peninsula. For these reasons
alone, the information provided here is important for the Peninsula,
historically, environmentally, sociologically and economically.
1 June 2007: Justice Awich
of the Belize Supreme Court denied PCSD's application to proceed with
judicial review of the approval of Ara Macao by the Belize Department of
the Environment. Justice Awich also assessed legal costs against
PCSD. PCSD did not have the funds to appeal Justice Awich's ruling,
although PCSD does believe that Justice Awich's ruling was in error.
A copy of the judicial decision will be made available when a
digital copy can be obtained.
2 April 2007: On Monday, 2
April 2007, the Peninsula Citizens for Sustainable Development (PCSD)
filed a lawsuit asking the Belize Supreme Court to overturn the decision
of the Belize Department of the Environment (DOE) approving the Ara Macao
Resort and Marina development at the northern end of the Placencia
Peninsula. PCSD also asked the court to grant an injunction to prevent Ara
Macao Development Ltd. from proceeding with the development.
PCSD’s suit is based, in part, on DOE’s failure to comply with Belize’s
environmental regulations.
PCSD also maintains that DOE unreasonably and irrationally approved the
development because it did not have critical information about
environmental issues such as downstream beach erosion, effect of the
development on the Peninsula’s marine environment (such as lobster, conch
and coral reefs), and whether Ara Macao and other new developments could
quickly use up the water supply that provides Placencia, Seine Bight, Maya
Beach, Independence and Big Creek with drinking water.
PCSD also argues that DOE’s approval failed to protect the public’s access
and use of the 66’ public reserve on the beach surrounding the
development, and that the development violates zoning for the area under
the Mango Creek/Placencia Special Development Area, as recognized by
Belize law.
A court date has been set for 20 April 2007 for judicial consideration of
PCSD’s claim.
Donations to the Ara Macao litigation fund may be made by depositing funds
into the PCSD account at Atlantic Bank, account number 100158838.
Donations may also be made by check
made payable to the Peninsula Citizens for Sustainable Development,
General Delivery, Placencia, Belize.
Money may also be wire transferred to
PCSD, using the following wiring instructions:
Bank of New York
36-63 Main Street
New York, New York 11354
ABA#: 021000018
For credit to Atlantic Bank
Swift Code: IRVTUS3N
Atlantic Bank Account No: 8900545925
For further credit to
Peninsula Citizens for Sustainable Development, Atlantic Bank Account no.
100158838
Please note that if wiring from the US,
this is NOT an international wire. The funds are wired to Bank of
New York which, in turn, transfers them to PCSD in Placencia.
The Peninsula Citizens for Sustainable
Development is a Belize non-profit corporation and grass roots community
organization of Placencia Peninsula residents concerned with the rapid,
and often poorly planned and executed, development of the Peninsula. PCSD
seeks to bring information about proposed developments to Peninsula
residents to ensure that all developments are environmentally sustainable
with respect to the fragile eco-systems of the Peninsula and its
communities and cultures.
Please contact PCSD at 610-4718 or
info@placenciadocuments.info for further information.
Peninsula Citizens for
Sustainable Development
Placencia, Belize
To: Belize Department of the Environment
Belize National Environmental Advisory Committee
Re: Proposed Ara Macao Development, South Stann Creek, Belize
Date: 3 May 2006
A number of serious issues have been identified by professional and
community reviews of the Environmental Impact Assessment (EIA) for the
proposed Ara Macao (a/k/a Scarlet Macaw) development (the “Proposed
Development”).
These issues include, but are not limited to:
-
Legitimacy of Public Consultation and Solicitation of Comments on the Ara Macao
Environmental Impact Assessment (“EIA”): On 17 March 2006, a
Public Notice for Ara Macao Resort & Marina appeared in
The Guardian
newspaper. The notice stated that the EIA had been completed and submitted
to the Department of the Environment (“DOE”) and that the EIA would be
reviewed by the National Environmental Appraisal Committee (“NEAC”) before
a final decision was made by DOE. The notice also invited the General
Public to review the EIA and submit comments.
On Sunday, 23 April 2006, a Public Consultation Notice for Ara Macao
Resort and Marina was published in the Amandala and other papers. This
notice stated that the EIA had been completed and that a Public
Consultation on the EIA would be held on Wednesday, May 3, 2006 at 6:30 pm
in Seine Bight Village.
On 20 April 2006, Mr. James R. Joslyn, a US citizen, spoke with Mr. Vince
Minnitti who is employed by the developer as its Director of Financial
Services. As part of a discussion between Mr. Joslyn and Mr. Minnitti, Mr.
Minnitti informed Mr. Joslyn that:
-
The developer had met with all members of Cabinet, who asked them to
drill two wells, among a few other requests, none of which were “deal
breakers,” according to Mr. Minnitti. In fact, Mr. Minnitti stated that
the developer was surprised that the Ministers had not asked about issues
such as beach erosion, which they were prepared to answer. Mr. Minnitti
also stated that the EIA was approved after the developer complied with
the Ministers’ requests.
-
There would be no environmental meeting in Seine Bight because the
people of Seine Bight did not want a public meeting. There would be a
meeting in Placencia on 3 May 2006, but strictly as a public relations
gambit because the Belizean government had already approved the EIA.
In May 2005, the Placencia Road Upgrade Environmental Assessment by Beca
International Consultants Ltd. (the “Road EIA”) was delivered to the Chief
Executive Officer of the Ministry of Works and Transport of the Government
of Belize. Photograph 2.10 on page 23 of the Road EIA shows the alignment
of the existing Placencia Road approaching the Placencia Lagoon, with
accompanying text describing the existing Placencia Road as passing
through “lowland savanna, wetlands and mangrove forest” located on the
site of the Proposed Development. The Road EIA then goes on to state that
“an area within this zone has recently obtained environmental clearance
for a tourism and housing project with amenities such as a golf course and
trails.” (see Road EIA, p. 23)
The date of the Road EIA clearly pre-dates the submittal of the EIA by the
developers by almost an entire year! Mr. Minnitti’s statements to Mr.
Joslyn concerning existing approval of the Proposed Development pre-dates
tonight’s public consultation by over two weeks.
Based on these facts, the environmental review process for the proposed
development, at best, lacks legitimacy, and, at worst, constitutes a fraud
upon the people of Belize. These facts also call into question the
legitimacy of the environmental review process for every development in
the country, not just the Proposed Development.
Further, these facts demonstrate an utter disregard for the health and
welfare of all residents of the Peninsula, and disdain for its communities
and cultures, and their right to have a say in their future.
We ask for an immediate explanation from DOE,
the Government of Belize and the developer.
-
Road EIA: The EIA conflicts with the Placencia Road Upgrade planned by
the Government of Belize under the Ministry of Works and Transport. As
presented in the Road EIA, that portion of the Placencia Road which passes
through the Proposed Development is built in environmentally sensitive
wetlands. Therefore, the Government of Belize in its Road EIA recommends
disturbing these wetlands as little as possible to avoid any adverse
effects resulting on the wetland areas outside the
existing [road] formation. (Road EIA, Section 6.3.1.d., page 77)
-
Terms of Reference: The EIA fails to comply with the Terms of Reference
(“TOR”) developed by DOE. The failure of the EIA to comply with the TOR
includes failure to:
-
Provide information on the overall management structure of the Proposed
Development
-
Establish seasonal water resource variations
-
Test temperature, DO and pH in the field rather than in a lab
-
Establish a sustainable safe, maximum yield for the confined,
pressurized aquifer
-
Provide an inventory of deep wells in the same aquifer
-
Provide an adequate pre or post EIA monitoring program for the
groundwater aquifer
-
Provide a separation of gray and black waters
-
Determine the nature and volume for the run-off of fertilized water from
the golf-course
-
Provide dimensions to scale of all marina related structures (both land
and marine based) and text justifying the size and scope of the marina
-
Provide restrictive covenants for the subdivision landowners.
No excuse is acceptable for failure to comply with the regulatory
requirements of the TOR.
-
Electrical Capacity: The EIA fails to address the lack of available
electrical capacity for the Proposed Development.
According to BEL, the developer’s use of electric transmission lines near
the property, including the line from Riversdale, is impossible because
the lines have no available capacity.
Instead, the developer will need to order and install a 115kv
substation to service the Proposed Development. Completion of the design
and build of this substation will require at least 3 years.
BEL indicates that the developer has not contacted BEL about its
electrical demands, which will equal the electrical demand of the entire
Belize City metropolitan area. This lack of planning for something as
basic as electric power is indicative of how this project has been put
together. If the developer plans to use an alternative form of power, the
EIA should have addressed this issue. Query: How does the developer plan
to construct a development of this magnitude without electricity? (See
Summary of Information Provided by Mr. Jose Marino, 2 May 2006)
-
Lobster Fishery: The EIA provides inaccurate information with respect to
the lobster fishery adjacent to the Proposed Development. This lobster
fishery provides a significant annual income to a number of lobster
fishermen in Riversdale, and the EIA fails to address in any way the
effects of the Proposed Development on the fishery or the fishermen (such
as from dredging and reclamation activities), or mitigation of these
effects.
Instead, the EIA merely states that “traditional users of the area are
mainly fishermen who use the main channel for fishing and boats traveling
from Seine Bight to Placencia. There is no foreseen threat to users since
homeowners are expected to be retirees and business persons with little
interest in fishing, except for recreation purposes and for small scale
consumption.” This statement is indicative of the lack of attention to
potential effects on local communities and their livelihoods throughout
the entire EIA. (See
Letter from Riversdale Fishermen Attesting to Health
of Lobster Fishery Adjacent to Proposed Development)
-
Siltation/Sediment Plume: The EIA inaccurately reports the composition
of sand in the natural channel in front of Proposed Development.
Independent testing found that the percentage of mud/silt in this channel
is at least 22%, and not 17% as reported in the EIA. A mud/silt
composition of 22% makes siltation curtains ineffective to control fine
sediments threatening corals, grass beds, fish, other marine life, and
southern beaches, and more appropriate measures must be proposed by the
developer. (See Review of
EIA for Coral Reef Impacts for Ara Macao Resort
and Marina, April 30 2006 by Todd R. Barber, Reef Ball Foundation, p. 61)
In addition, high silt and peat content as indicated by reported borings
necessitate filters and “silt-ponds“ (e.g., settlement ponds) to control
the silt and turbidity of reclamation discharge. The EIA for the Proposed
Development completely fails to address the need for settlement ponds in
this context. (See
Comments of Dr. Thomas Williams, University of California at Berkeley, pp 8-9)
(Note: the amount of peat and silt that will be deposited in the sediment
ponds will make the settlement ponds completely un-useable for building.)
In addition to marine life destruction, improper siltation and sediment
control can destroy businesses and livelihoods in adjacent areas by
destroying lobster, conch and grass beds, and by making the area
unattractive for divers, snorkelers, anglers, kayakers and beach and
nature enthusiasts.
The EIA includes no discussion of a Predictive Monitoring Program which
seeks to prevent harmful effects of siltation rather than mitigate the
impact once the harmful siltation has already occurred.
Predictive Monitoring
-
Shore Erosion/Sand Starvation: The EIA does not include sufficient
information and analysis of the real threat of downstream shore erosion
and sand starvation of beach properties, including possible accretion of
sand over coral reef adjacent to the Proposed Development. Instead, the
EIA attempts to ignore or minimize both of these issues. However, the
effects of jetties, breakwaters and groins are clearly evident along the
coast.
Further, the developer’s engineers, Shabica and Associates, recognize the
issue of sand starvation of downstream beaches in the annexes, but offer
only an ineffective and unrealistic solution to the problem – that of
perpetual maintenance dredging, filling and physical movement of sand.
(EIA Annex, p. 88) Further, pictures presented by Shabica and Associates
in the Annex as evidence of lack of erosion downstream from existing
structures actually do show evidence of erosion – that of lost older
trees. (EIA Annex, p. 80).
In addition, as noted by Barber, “sand by passing cannot guarantee the
lack of downstream erosion to the south, nor can it guarantee that sands
do no over-accrete to the north . . . [and] a very real possibility
[exists] that sand will try to by pass the channels offshore and this sand
may or may not make it back to shore south of the structures. If it does
not make it back to shore, erosion will be the result. Either way, this
sand may flow over natural reefs offshore, killing them. Additionally, the
sand that accretes to the north may back up sufficiently to cover the
natural reefs.” (Barber, p. 66)
Finally, the developer contends that its coastal works will reduce
sedimentation of coral reefs by covering eroding areas with coarse sands
and that the coarse sands will lead to reef recovery. However, as also
noted by Barber, “the eroding beach sands all contain less than 2% of silt
(sieve smaller than #100). So, at best, any gains will be offset by the
perpetual dredging activities. Claims that the development will aid in the
recovery of the reefs due to reduced sedimentation (as presented) are
unfounded.” (Barber, p. 69)
Barber recommends an independent evaluation of the down stream erosion
potential, upstream over accretion possibility and offshore sand transport
over reefs by Dr. Lee Harris of The Florida Institute of Technology who is
a renowned expert on the effect of coastal structures. Dr. Harris can be
reached at lharris@fit.edu. (Barber,
p. 68)
-
Water Quality and Quantity: The EIA uses inadequate estimates of the
quantity of water that will be required to operate the Proposed
Development. In addition, the EIA well water quantity and quality test
results are suspect.
-
Water Quantity: The EIA assumes that each resident and guest at the
Proposed Development will use an average of 34 gallons of water per day,
without differentiating among guests, employees and residents. The EIA
instead estimates water usage by facility, without breaking out the number
of employees, residents and guests in each facility, making it impossible
to perform intelligible calculations based on actual likely water usage.
However, even ignoring this flaw, it is clear that water usage is grossly
underestimated. For example, the highest water usage of 47.5 gallons per
day is estimated for the golf course houses, which are the only units
likely to actually house resort residents as opposed to guests. Instead of
47.5 gallons per day, these residents are more likely to use 80-100
gallons a day, which is the average water usage for residents in the US.
(Note: even the EIA approved for the Coco Plum development on the
Peninsula uses an estimate of 75 gallons per day per person. See also,
Comments by Mark Chernaik, Ph.D, Mercedes Lu, Q.F., May 2006
In addition, an almost 80% underestimation of the quantity of water
needed by the Proposed Development results from the developer’s use of an
average daily water consumption of 34 gallons per day instead of 150 to
179 gallons of water per day for the 5,810 tourists in the condos, villas,
golf course and club house units, hotel, casino, bars and restaurants.
(See page 3,
Environment and Tourism: Examining the Relationship between
Tourism and the Environment in Barbados and St. Lucia,
reporting that in St. Lucia, the average resident uses on average
of 50
gallons per person each day, while hotel residents use up to 150 gallons
per person daily. Also, Barbadians use 73 gallons per person daily and the
average tourist 179 gallons per person per day.)
Further, the amount of water needed for employees cannot be based on
occupancy rates since a certain number of full-time employees will be
working and living at the resort regardless of tourist occupancy.
(Again, it is impossible to determine accurately how many guests,
tourists, residents and employees will be at the resort on a daily basis
since the EIA fails to differentiate among these groups in its occupancy
information. For example, Table 5.1 of the
EIA reports that 5,648 people can occupy
the Reception and Commercial Areas at full occupancy, but doesn’t tell us
who these people are or what they will be doing.)
-
Adequacy of Aquifer: The adequacy of the aquifer the developer proposes
to use to provide drinking water should have been tested using an aquifer
test rather than a “well” or pump test. This involves pumping for four to
ten days at a rate of at least equivalent to the project supply
requirement at capacity. As no other deep boring information is available,
no confirmation of the adequacy of Wells 1 or 2 is possible from the
information in the EIA, especially given the gross underestimation of
water quantity required by the resort as discussed above. (See
Williams p.
5)
Further, the ground province of the southern Belize coast and cayes is
thought to be almost lacking groundwater resources. “A persistent perched
water-table aquifer exists in the extensive sand beaches all along the
coast and similar aquifers exist on the larger cayes, but the amount of
fresh water in them is not large . . .”
-
Quality of Well Water: The well water testing results may be too good,
especially in terms of the TDS and conductivity results for ground water.
Further, the pH of the water is acidic (which is not specifically
mentioned in the text of EIA, only in the water quality testing tables),
requiring special handling in terms of pipes and conduits. In addition,
treatment over and above the proposed addition of chlorine is necessary
before this water can be used as drinking water. (See
Williams,
pp 5-6)
-
Wastewater/Sewage: The gross underestimation of water quantity needed
for the Proposed Development clearly means that the amount of
wastewater/sewage has also been grossly underestimated. In addition, the
EIA does not address the quantity of waste water and sewage from 400 boats
in addition to those generated on land (as required by the TOR). (See
Williams, p. 7)
The BESST units chosen by the developer to treat wastewater/sewage are
definitely able to treat water and sewage to standards at or above those
required by Belize law. However, if the BESST units are overloaded by
actual flows 10-50% above what has been estimated in the EIA, the treated
effluent may contain higher levels of pathogens than permitted by Belize
law, resulting in potentially serious health hazards for local
communities, employees and residents and guests at the Proposed
Development. (See
Williams, p. 7)
-
Water Quality Monitoring: The EIA includes an extremely ineffective
water quality monitoring plan for coral reefs which sets critical levels
for phosphate at 100 times those acceptable for coral reefs and nitrate
levels at 10 times higher than those acceptable for coral reefs. (See
Barber, p. 55)
Also, no baseline for monitoring has been established, especially in the
Placencia Lagoon, because only one site in the Lagoon was initially tested
by the developer (a site not near the Proposed Development) and is not
included in the list of sites to be monitored in Figure 20-1 of the
EIA.
Further, water quality monitoring is only mandated for a period of 4
years, a period which could very well expire before the Proposed
Development is fully completed.
-
Cumulative Impacts: The EIA completely disregards and fails to address
the serious environmental and social/economic effects of all proposed
developments in the Placencia Peninsula area.
These developments will bring the resident and guest population of the
Peninsula to well over 22,000 persons within 4 years if the Proposed
Development is approved. The resident population of the Peninsula is
currently under 2,000, and its education, healthcare, police and fire
protection resources are already stretched to the breaking point.
The EIA completely fails to recognize or address problems local
communities will encounter in attempting to educate, house and protect the
hundreds of additional people the Proposed Development and others will
bring to the Peninsula. (As an example of the developer’s complete
disregard for local communities, the EIA answers the question of the need
for increased security by stating that it will provide its own security
within the boundaries of the Proposed Development, completely ignoring the
increased security problems it will cause for area communities.)
Belize law requires NEAC to consider the cumulative effects of all
proposed developments in the area of the Proposed Development. However,
the EIA merely (and inadequately) states in Section 18.2 that “the
determination of potential cumulative impacts, as required by the TOR, is
difficult to quantify since data is limited due to the fact that all
projects have not been subjected to the environmental clearance process.”
How can NEAC intelligently assess cumulative impacts when the EIA provides
no substantive information about those impacts? The EIA could have
reported on the number of developments slated to come on-line on the
Peninsula in the next 2 or 3 years, which is information readily and
easily obtainable from a basic search on Google using the search terms
“Belize real estate.” Internet information on the size of these
developments is also readily obtainable, as are permits issued by DOE. Had
the developer gone to the trouble to obtain this information, projections
could have been made for items such as estimated increase in population,
solid waste and waste water generation, water consumption, electrical
consumption, demands on infrastructure and educational, health and
security factors. Further, if the developer cannot obtain this information
from DOE, something must be very wrong with the EIA process in southern
Belize.
-
Marina Flushing: The EIA’s conclusion that “successful” flushing of the
marina can occur in 2-3 days is suspect given the small, less than .5
meter maximum normal tides, and the fact that the water quality model for
the marina uses a clean and clear channel without boats, while the
successful project anticipates 307 boats up to 30+m length which will
severely reduce the turnover/flushing of the lagoon/marina. (See
Williams,
p. 9)
-
Solid Waste Management: The EIA fails to provide any analysis of the
Placencia dump and grossly underestimates the amount of solid waste that
will be generated by the Proposed Development.
-
Placencia Dump: The EIA fails to answer questions related to: (a)
whether the Placencia dump has the capacity to absorb up to 1.7 million
pounds per month of additional garbage that will be produced by the
Proposed Development at capacity, (b) the financial ability of Placencia
Village to acquire necessary equipment, employees and management expertise
to professionally manage the dump given the complete lack of taxing power
of the Placencia Village Council to raise revenue for the dump, and (c)
the amount of leaching that may occur at the dump with this amount of
additional garbage, how that leaching can be mitigated, and the effects on
the environment of surrounding communities if leaching problems are not
addressed.
The developer must assure that the location used for solid waste disposal
is a properly managed and funded land fill, and not a mere waste dump.
This includes separate (and safe) disposal of hazardous chemicals and
substances under an approved hazardous waste management plan (not included
in the EIA), environmental protections such as liners to control leaching,
segregation of garbage and a viable recycling plan.
The Road EIA describes the Placencia dump as a “visual and ecological
blight on the landscape . . . [that] is unnecessarily large in area. There
appears to have been little attempt to manage its use and operation or
contain the dump and the site is badly in need of some form of
rehabilitation work.” (See Road EIA, p. 33)
-
Solid Waste Estimates: The EIA solid waste projections are based on 3
pounds of garbage per day per person for residents, guests and employees.
The developer selected this number based on the average of the amount of
garbage generated in Belize metropolitan areas, apparently excluding San
Pedro where the average daily amount of garbage per person is 4.8 pounds
per day. The amount of garbage produced by San Pedro is a much more
accurate number for residents and guests of the Proposed Development, who
will primarily be from North America and possibly Europe, where the
average amount of residential garbage produced per day is 4.5 pounds.
(Department of Environment Quality for the State of Oregon)
Further, tourists produce even more solid waste per day than residents
because they have no stake in the sustainability of the country as would
longer-term residents. And, guests visiting the resort on a day basis
have even less of a stake than overnight guests.
One
hotel and casino in California with 781 hotel rooms reported solid waste
generated per day at 11 tons or 22,000 pounds – or over 28 pounds of
garbage per day per hotel room.
Based on this report, the Proposed Development will have 1,041 rooms,
generating 29,148 pounds of garbage per day, or over 7 pounds per day per
guest based on the occupancy numbers in the Proposed Development for the
condos, villas and hotel. Clearly, solid waste estimates provided by the
EIA are seriously underestimated, further increasing the need for a
professionally managed solid waste management facility, and not a waste
dump about which no information has been provided by the developer. (The
developer also seeks to hide the fact that it will produce a minimum of 6
times the solid waste produced by the local Seine Bight and Placencia
communities by including Dangriga in its solid waste calculations.)
-
Wetlands: The EIA completely fails to recognize or address significant
destruction of wetlands by the marina, the golf course and diversion of
the Placencia Road. Wetlands are among the most valuable and productive
ecosystems on earth and provide biodiversity conservation, nursery and
breeding grounds, improved water quality, flood mitigation, groundwater
recharge, foreshore protection, recreation, aesthetic values and
uniqueness for communities on the Peninsula.
As recognized in Section 2.8.2 of the Road EIA, the Proposed Development
is located in the Mango Creek and Placencia Special Development Area (SDA).
The report for the SDA was approved in 1997, and included the objective of
protection of wetlands within the SDA. Further, that portion of the
Proposed Development in which the golf course, a portion of the marina and
the road diversion are located is within an area designated by the SDA as
a Protection Reserve II. The land use zoning established by the SDA report
is still effective.
Further, the Road EIA recognizes the sensitive nature of the wetlands
environment located at the Proposed Development and adopted “a reduced
design speed of 80 kph in order to avoid excess widening into the
surrounding wetland. The construction area will be contained totally
within the existing surface area. The completed design will provide a seal
width of 7 metres, resulting from a reduction in the shoulder width. This
avoids any new adverse effects resulting from the disturbance of wetlands
areas outside the existing formations.” (See Road EIA, p. 77)
-
Surrounding Communities: As mentioned in the previous section on
Cumulative Impacts, the EIA fails to adequately assess the social and
economic effects on surrounding communities, including police and fire
protection, healthcare, education, and significant price increases for
commodities and land. For example:
-
Police Protection: The Peninsula’s very tiny police force of 4-6
officers and constables is already overwhelmed by existing crime, and
lacks basic tools necessary to do its job, such as vehicles, radios,
telephones – even office supplies and computer equipment. If the
Peninsula’s police force can’t deal with existing crime, how will they
cope with the large numbers of construction workers who will be needed to
construct the development, and the hundreds of employees who will be
housed somewhere in the area after completion?
-
Fire Protection: Fire protection does not currently exist at all in the
area.
o Healthcare: One nurse and one Cuban doctor currently provide all the
available medical care for the entire Peninsula. It is laughable to assume
that two people can possibly provide the medical care that will be needed
by the employees and families of the Proposed Development – not to mention
all the medical supplies that someone must purchase, pay for, and store.
-
Education: The schools in Seine Bight and Placencia are already
overcrowded, and Santa Cruz doesn’t even have a school to educate its
children. School attendance is mandatory in Belize. But, who will provide
this education when there are already too many students for the existing
schools? How will the Government of Belize find the funds to construct a
new school at Santa Cruz, expand the existing schools in Seine Bight and
Placencia and pay the additional teachers that will result from the
developer’s project – without any financial impact or responsibility for
that impact on the developer?
The developer is asking for permission to use an enormous amount of the
public’s natural resources for its own potentially enormous private gain.
A just and equitable amount of that enormous private gain should be
available to compensate local communities for these resources and to pay
for the tremendous burdens imposed on them in order for the developer to
realize its enormous profits.
However, the developer’s lack of concern for the potential impacts of this
size of a development are amply demonstrated by mitigation measures
detailed in pages 13-11 and 13-12 of the EIA which completely fail to
recognize or respond to issues related to the impact of the Proposed
Development on local communities. In addition, in response to the
potential impact of the location and size of the Proposed Development, the
developer states that the Proposed Development is “low impact and low
density” compared to other urban developments and that the residual impact
of the size and location of the development is of low magnitude! When did
a 20 mile peninsula with a population of under 2000 become an urban area?
(See,
EIA Table 13.6)
-
Economic Impact on Local Communities/Local Employment: As has been amply
demonstrated throughout the world at enclave developments similar to the
Proposed Development, and by the cruise ship industry in our own backyard,
large scale tour operators from the well established and well connected
elites are favored by large scale developments such as the proposed Ara
Macao.
We have all watched as the skiffs which originally carried cruise ship
passengers a few at a time to snorkeling sites were replaced by large
catamarans carrying hundreds of people. We have all seen the hair
braiders, local craftsmen and other local vendors pushed beyond the iron
gates of the Tourist Village, where signs warn tourists that they leave
the safety of the Tourist Village sanctum at their own risk. The simple
fact of the matter is that large scale operations want to control all
aspects of their guests’ tourist experience so that they can reap most, if
not all, of the financial rewards from that experience. Large scale
developments such as Ara Macao want their guests to eat at resort
restaurants, drink at resort bars, take resort tours and buy resort
souvenirs. They do not want competition from local tour guides, local
restaurants, local bars, or local craftsmen.
Further, local entrepreneurs and small investors do not have the liquidity
or access to affordable capital to finance luxury fishing boats, climate
controlled coaches, custom-designed furnishings and other capital items
necessary to compete against well-capitalized resorts such as the Proposed
Development, most of which also enjoy substantial development concessions,
allowing them to import much of their operating inventories duty free.
Instead, most of these local entrepreneurs and small investors have
invested their life savings, the only capital to which they have access in
addition to their own labor – both of which have earned Belize the
reputation as a prime eco-tourism destination that it enjoys today.
The EIA fails to recognize this issue of marginalization of local
independent businesses and investors, or to offer any mitigation for the
effects of this marginalization other than to hold out the carrot of
“increased employment.” However, many of the people who currently own and
operate their own businesses have no desire to be forced to become an
employee of a development so out of scale and character with their culture
and environment. But, even if they do, the EIA fails to provide any
details of the kind of employment they might find at the Proposed
Development. Are the jobs that will be provided temporary or seasonal,
full-time or part-time, salaried or hourly, skilled or unskilled? For
example, will an experienced and skilled fly fishing guide be a permanent
employee, on-call, seasonal/temporary? Will he receive private health care
benefits, a pension, a paid vacation every year? Will he be required to
live at the Proposed Development, or expected to commute? Can he afford to
commute, and if he is required to live at the Proposed Development, where
will his family live? Will he earn as much money for his family as he does
now with his own boat, his own gear and his own livelihood?
How will managerial and skilled employees be recruited? From where will
they be recruited? If there are no skills available on the Peninsula, will
training and educational programs be made available so that these jobs may
eventually be filled by local residents? How will the free movement of
workers under CARICOM impact on the employment opportunities available to
Peninsula residents?
Again, the EIA abysmally fails to recognize or address any of these
employment related issues or impacts on local communities.
-
Casino: The EIA fails to address the direct and indirect labor
requirements of the proposed casino or to provide necessary operational
information about the proposed casino and night club, such as number of
seats in the proposed casino, casino floor space, size of night club, and
other services in the facility such as restaurants, number of bars, and
the source of casino and nightclub patrons.
-
Casino Labor Requirements: Direct and indirect labor requirements for a
casino far exceed the levels indicated in the EIA and will generally
require much higher levels of experience and skills than can be met by
general training. The EIA does not address the source of these employees,
wage scales, the need for advanced training in order to hire Belizeans and
the effect of the CARICOM free movement of labor, which may result in most
mid to upper level management positions in the casino being filled by
Caribbean nationals and not Belizeans.
-
Casino Operational Information: Operational information is necessary to
evaluate water capacity, sufficiency of solid waste management (as
discussed above), waste water treatment capacity and management, and
financial viability of the Proposed Development. Also, Table 5.1 of the
EIA calculates occupancy of the casino at 1,000 persons in addition to the
number of guests, residents and employees in the hotel, villas, condos,
and golf course homes. Since information such as number of seats and floor
space of the casino is not provided, it is impossible to determine the
population base that will be needed to support the casino. However,
assuming 500 seats (or half the reported capacity of the casino) a
population base of approximately 18,000 people is necessary to make the
casino economically viable. The EIA does not discuss where this population
base will come from, strengthening local suspicions that one of the
primary purposes of the Proposed Development is as a cruise ship
destination as discussed below in the section on Undisclosed Uses of
Proposed Development Facilities. In any event, operational information is
necessary in order to adequately evaluate carrying capacity.
Golf Course: The EIA is wholly lacking in any specific details about the
golf course other than the location of the club house, the acreage and the
grass that will be used as turf.
Significantly, it fails to address the nature and volume of the expected
run-off of fertilized water from the golf-courses as required by TOR, or
to provide details about the pesticides and insecticides that will be
actually used on the golf course. The list of pesticides that may be used
on the golf course is merely a list of all pesticides and insecticides
authorized for use in Belize.
Section 1.04 of the TOR requires information on pesticides that will be
used, not any and all pesticides that might be used. Therefore, the EIA
also does not comply with Section 1.04 of the TOR. This is not a mere
niggling matter because neither DOE nor NEAC can evaluate the impact of
pesticides that will be used on the golf courses without knowing what
those pesticides are – or what pests they are intended to destroy.
Further, no mention is made of any specific controls to reduce the use of
pesticides and insecticides such as Integrated Pest Management, or
specific grasses that are not prone to significant damage from tropical
insects.
Also, as with other EIA sections dealing with water use, we suspect that
the amount of water that will be required for the golf courses has been
significantly underestimated since
UNESCO reports that 18-hole golf courses situated in the tropics can
use up to 575,000 gallons of water per day.
Further, the EIA did not include the water required for the golf course in
its calculation of water demand of the project. The Executive Summary
mentions it is expected that some 325,000 gallons of water per day at full
operation, equivalent to 1,23 cubic meters per day or 450,000 cubic meters
per year, which is only half of the water required to irrigate the golf
course, which could be even higher considering the high evaporation rate
in the weather conditions of Belize. (see
Chernaik, p. 3)
However, it is impossible to adequately assess the water use issue
because the EIA includes so few details about the golf course that are
essential to an
assessment of water use, including course layout, irrigation system
design and control, fertilization program, pest management, and mowing.
What we do know is that the EIA describes Bermuda grass as the preferred
turf grass rather than other more environmentally friendly grasses such as
Seashore paspalum (Paspalum vaginatum) which has relatively low fertiliser
requirements, (up to 50% of that needed by hybrid Bermudagrass), and will
tolerate salt water and other alternative irrigation sources, e.g.
recycled water.
In addition, we are uncertain of the relevancy of the EIA’s almost
verbatim (and without citation) publication of
The
General Description of Construction Line Items from the American Society
for Golf Course Architects from the Society’s Website and which consumes about one-half of Section 16 of the EIA).
Finally, no mention is made in the EIA of seeking certification as an
environmentally sound golf course by the Audubon Cooperative Sanctuary for
Golf Courses certification program. (http://turf.lib.msu.edu/2000s/2002/020925.pdf
and
www.audubonintl.org/programs/acss/CACS%20List%20by%20State.pdf).
The proposed golf courses present such a significant threat to the fragile
wetlands and Lagoon environments that a separate EIA should be required
for the golf courses.
Economic and Financial Viability/Project Abandonment: The EIA fails to
include any information about the economic viability of the Proposed
Development with respect to the financial ability of the developer to: (a)
complete the project if approved; (b) comply with significant ongoing
monitoring requirements given the serious environmental impacts that will
result if problems are not identified as soon as they develop; (c)
continue maintenance dredging and beach sand filling in perpetuity (as
long as groins and channel remain); (d) attract the necessary number of
visitors for economic viability of the proposed casino and golf course; or
(e) provide a fund for closure of the project and mitigation of negative
environmental impacts (such as removal of the breakwater jetties) if the
project is abandoned.
Development Schedule: The EIA fails to include adequate information on
the development schedule for the Proposed Development in terms of which
buildings will be completed first and when infrastructure will be
completed. Lack of detailed information on the development schedule for
the Proposed Development means that DOE cannot be sure that Phase I is
complete before giving approval to the developer to start Phase II. This
lack of information also raises suspicions that the developer does not
intend to actually develop the project, but instead intends to immediately
sell the property once its value has been substantially increased by an
approved development plan. This lack of detailed information also raises
the suspicion that the developer did not believe that its full proposed
development plan would be approved, which resulted in the developer asking
for approval of a much more intensive development in the hope of getting
what it really wants.
Project Financials: The EIA fails to provide any information about
whether project financials are based on the same assumptions as those used
in the EIA. This information is necessary to fully assess whether the
projections provided in the EIA to the Belize government are realistic
ones, or were developed solely for the purpose of obtaining development
approval.
Undisclosed Uses of Development Facilities: The sheer size and scope of
the project in relation to the population of southern Belize, including
all new developments on the Peninsula, has created a very strong local
suspicion that one of the primary purposes of the Proposed Development is
to provide a cruise ship passenger destination for cruise ships docking at
Big Creek or other proposed cruise ship ports in the region. The EIA
deliberately avoids addressing the issue of the permanent and temporary
population base necessary for a development of this size. If suspicions
are correct, the EIA must be completely reworked to include assessments of
the wide-reaching effects of large numbers of day visitors from cruise
ships, including, as illustration, but not as a limitation, water, solid
waste management, sewage and local employment. In any case, the EIA must
address the issue of day visitors with respect to all of the issues
discussed above, including water consumption, garbage, waste water, and
impact infrastructure.
More information on the above issues is provided in the enclosed
documents, which include:
EIA Review for Coral Reef Impacts, Todd Barber, Chairman, Reef Ball
Foundation
Comments of Dr. Thomas Williams, University of California, Berkeley
(also attached as Appendix I to the enclosed EIA Review by Todd Barber)
Comments on the Environmental Impact Assessment (EIA) for the Proposed Ara Macao Development, South Stann Creek, Belize, by Mark Chernaik, Ph.D,
Mercedes Lu, Q.F. May 2006
Statement of Lobster Fishermen from Riversdale
Report on Investigation into Availability of Electrical Supply to the
Proposed Development, including information provided in a phone interview
with Mr. Jose Moreno, Planning and Engineering Dept., BEL, 2 May 2006. Tel
227-0954
Mango Creek Special Development Area Map
As demonstrated by the issues identified above and in the enclosed
documentation, the amount of missing, inadequate and inaccurate
information provided in the EIA for the Proposed Development is
staggering.
Also, please note that the list of issues identified above is not an
all-inclusive list, but rather represents some of the most serious
problems of the EIA identified by the community and its consultants. Other
very serious issues also need to be adequately addressed by the EIA,
including, but not limited to:
-
The amount and effect of fertilizers, insecticides and pesticides that
will be drained or leached into the Placencia Lagoon through the 15’ wide,
6’ deep and 9,504 feet long drainage “ditch” the developer proposes to dig
to channel untreated drainage from the road and the golf courses into the
Lagoon
-
The establishment of an adequate water quality baseline so that a
meaningful environmental monitoring program can be implemented
-
The possibility of saltwater intrusion into the ground water from
over-pumping of well water for the aquifer (see
Chernaik, p.4)
-
Hurricane evacuation and/or shelter for residents of the Proposed
Development, and hurricane evacuation of residents living south of the
Proposed Development
-
Disposal of sludge from the waste water treatment facilities (which is
not addressed in the EIA)
-
Possible contamination of dredged soils from banana and shrimp farm
operations making the dredged soils unsuitable for use as fill
-
Potential breach from Caribbean to Lagoon and impacts of such a breach
-
Impacts on coral reef from land-based activities
Consequently, the EIA for the Proposed Development does not provide a
rational basis on which to make an informed decision about the Proposed
Development. Therefore, NEAC must deny the Proposed Development based on
this EIA. If the developer still desires to proceed, it must submit a new
or substantially revised EIA that adequately and reasonably addresses all
relevant issues, including, but not limited to, those outlined above.
Therefore, we respectfully urge NEAC to recommend denial of the Proposed
Development until the developers comply with the laws of Belize regulating
the environmental and social/economic impacts of their Proposed
Development on our environment and our communities.
cc: BACONGO
Placencia Village Council
Seine Bight Village Council
Independence Village Council
Ministry of Natural Resources and the Environment
Belize Tourism Industry Association – Placencia Chapter
Belize Tourism Industry Association (national office)
Belize Eco-Tourism Association
Belize Audubon Society
Friends of Nature
Belize Zoo
TIDE
BELPO
|